CUBA WASTEWATER TREATMENT PLANT

Year: 2012

Description: to plan, design and construct a wastewater treatment plant in Cuba in Sandoval county

City: Cuba

County: Sandoval

Amount budgeted: $200,000.0

Amount spent (through June 23): $79,943.0

Arts in public places allocation: $0.0

Reauthorized to the same or another project: $0.0

Amount returned to state (through June 23): $0.0

Balance as of June 23: $120,057.0

Project status: 6/3/15 Village/Sandoval County selected SMA for the prepared RFP for the design of Phase 2. Agreement for engineering services will go to the June 18th Commission meeting.