New Mexico's Capital Dilemma

Explore New Mexico's bond-funded capital outlay projects. For stories about the data, go to New Mexico In Depth.

ACOMA PUEBLO SKYLINE LAGOON SYSTEM, RET

Year: 2011

Description: The time of expenditure for the Indian affairs department project in Subsection 13 of Section 66 of Chapter 42 of Laws 2007 to plan, design, construct and renovate the skyline lagoon system at the Pueblo of Acoma in Cibola county is extended through fiscal year 2013.

City: Acoma Pueblo

County: Cibola

Amount budgeted: $50,000.0

Amount spent (through June 23): $40,000.0

Arts in public places allocation: $0.0

Reauthorized to the same or another project: $0.0

Amount returned to state (through June 23): $10,000.0

Balance as of June 23: $0.0

Project status: Have not received signed agreement as of 9.14.2011 Grant Agreement Amendment sent out to Organization for signataure on 4-28-2011. no activity as of 3/20/12. The work performed under this JPA total 40,000 and was used to match other funds to purchase a 60 mil textured HDPE synthetic liner on the west cell Lagoon 1 of the Skyline Lagoon System. Lagoon work consisted of: transfer of lagoon effluent to other lagoon cells, sludge removal, overexcavation of lagoon bed, replacement of lagoon bed with clay soil, removal of concrete lining, recompaction of lagoon floor and dikes with proper sloping requirement, installation of synthetic liner, final grading, and startup procedures for lagoon wastewater treatment. RW 6-14-13. Appropriation balance 10K will be reverted when audit is complete.